ABC7 News explains, "Starting next weekend and on into November Caltrans will be carefully packing explosives and imploding 13 marine foundations still standing five stories tall under the water in the Bay. The implosions will affect pedestrians and bicyclists the most -- the path across the eastern span will close the entire week before each set of blasts starting Sunday, Aug. 27. So one week open, one week closed through the fall."
Here are the closure dates for the pedestrian and bike path:
Week of Aug. 27
Week of Sept. 10
Week of Sept. 24
Week of Oct. 8
Week of Oct. 22
Week of Nov. 5
There will be intermittent closures on the Bay Bridge for traffic on:
Sept. 2
Sept. 16
Sept. 30
Oct. 14
Oct. 28
Nov. 11